During construction of the SICK Inc. Bloomington Campus, finishing work was required throughout the building’s expansive atrium. Crews needed continuous access to structural ceiling beams and skylights, as well as the full height of the concrete walls—from floor level to the very top of the space. The scale of the atrium required an all encompassing access solution capable of supporting work across the entire interior.

Infinity Scaffold designed and installed a massive frame scaffolding dance floor that provided full perimeter and ceiling access. The scaffold set had working deck levels every seven feet to accommodate the entire space. Small rolling scaffold sets were then created at the top of the dance floor to give easier access to the skylights.
Key elements of the solution: